200 Homes Manchester Road – Objection
The Parish Council has sent its formal objection to Warrington Borough Council
We urge all residents to review the plans, and make your opinions known.
On Behalf of Rixton with Glazebrook Parish Council, and the residents
The Parish Council holds a strong objection to planning for the building of 200 houses, off Manchester Rd (outline planning reference 2026/00889/OUTM
Local Impacts
Housing
The current number of occupied households is approx. 747 (plus 110 that are currently being built. This would be an increase of around 41% of households if 200 are built (including the 110 currently in construction.) If the parcel of land to east of the property is also developed – this would more than double the size of the rural village.
This will impact on the number of residents (from approx.1,650 to circa 2400) and an increase in cars, and all the subsequent drain, on extremely limited resources.
With no known planned changes to the infrastructure (including the Section 106 proposals), the Parish Council would strongly object to this application and adds the following concerns to those mentioned above.
Affordable Housing – Current housing delivery, particularly on greenfield is not genuinely affordable as developers seek permission for larger family and executive homes in more affluent rural places. It is also important for rural places to have more ‘genuinely’ affordable homes, meaning in perpetuity low-cost social housing.
The definition of grey belt land is subjective. The Grey Belt Assessment document provides an overall assessment of “Strong Contribution.” This is based on scores of one “Strong contribution,” two “No contribution,” one “Moderate contribution” and one “Weak contribution.” The Parish Council would strongly challenge this scoring assessment.
Warrington Borough Council has not identified this area of land in its Local Plan. There are suitable brownfield sites around the borough with capacity for over 11,000 homes.
Amenities
The impact on local school, children’s play area, village green area. The school in Hollins Green is already oversubscribed at 32 children per class, there is also a lack of senior school places, and all require some form of public transport.
The impact on other local facilities (there is one small shop in village). Village amenities are barely suitable for the current number of residents of the villages of Glazebrook, Hollins Green and Rixton, unless new facilities are built during any construction phase. With limited existing amenities, there is no economic advantage within the development to the village, new residents will work outside the area and use amenities in other parts of the northwest.
Warrington Borough Council have recently published a deficit of £350m and will be reducing and ceasing existing public services over the next few years, including levels of street lighting, grass cutting, refuse collection/street cleaning. For several years, the Parish Council have requested additional waste bins, and have been told it is not possible as this will require investment from WBC to increase its machinery/manpower etc. How will future bins and domestic waste be collected?
The Economic Benefit statement indicates £7.5m of salaries, £4m of expenditure. Warrington will not benefit from this, as the nearest large amenities are Salford/Trafford/Manchester. Villagers currently use these for ease/quickness.
The Transport Assessment references the benefits of short distances to these amenities from the new proposed development, without any consideration to current usage. The village shop is 420 meters, however, how could the village shop cope with the demand for 200 loaves of bread and 200 pints of milk, every day? There is no mention of the difficulty residents, who would live in the new houses, will have in accessing the amenities north of the A57. The new development would be an isolated island of land, with the Ship Canal and A57 limiting access. Pedestrians would have to cross a very busy dual carriageway to access the amenities highlighted in the assessment document.
The impact on local health services. There are no public health facilities in the area, Dr’s, Dentists, Chemists etc all require some form of transport to reach, and all are already oversubscribed. The Surgery in Culcheth already has 3 week waiting times to see or speak to a Dr, there is also only 1 Dentist locally that will take on NHS patients.
Traffic
The impact on local roads, increasing existing issues with parking and congestion. The lack of public transport, with a single bus route currently the number 100 bus which goes to and from Warrington or the Trafford centre, and a limited service run by WBC some evenings. There is no service on Sundays. There is a train service in Glazebrook but that is not within walking distance for most and the service doesn’t run on Sundays and only stops at this station every 2 hours.
Access to the proposed new housing estate will potentially create traffic issues as there are limited access points and would certainly require yet another set of traffic lights.
Warrington is road dependent with traffic congestion, accidents, poor air quality, high incidence of respiratory disease and other poor health indices. In future more integrated transport infrastructure is required, with walking and cycling being prioritised and better enabled, along with public transport services such as bus and rail, which is already extremely poor in the area.
The impact on traffic, congestion / travel time and air quality has been underestimated. It is indicated that the proposed development is forecast to generate 56 two-way vehicle trips during the PM peak. This is equivalent to just under one additional vehicle movement every minute. For a development of 200 houses, of which many households are likely to have multiple vehicles, the number of trips is extremely low.
If the development propose that residents will walk or cycle to local amenities residents will use cars and resulting in increased traffic flow through Hollins Green causing congestion and parking problems. Glazebrook Railway Station only has 6 car parking spaces and does not have the capacity for increased multi-modal usage without further parking provision Housing.
The proposal will require additional traffic lights and will subsequently and adversely affect the flow of the traffic on the main east bound road artery, in/out of Warrington.
Section 106
The Section 106 Heads of Terms does not make any reference to ring fence any monies that can be used to improve the current infrastructure. This was promised by Peel to the Parish Council on the 15th of June.
The issues with the school are not addressed. Peel commented (15th June) a new school/extension could be built, however there is no room for this to be done, so any monies will not benefit the primary school, and only the secondary schools – which are not in the village.
Transport contributions are not identified to benefit the villages (or the new development)
There are no plans for healthcare contributions for the villages, these monies will go to central Warrington areas, or neighbouring wards.
The agreement plans to deliver an off-site financial contribution to Holcroft Moss Mitigation – this is not in Rixton and Glazebrook, but in a different ward.
Sports Pitch – is not identified where this will be and who will benefit.
The lack of ringfenced future section 106 agreements is a major concern. The area did not receive a single penny of resource from the 110 homes development. All section 106 monies went to neighbouring wards.
For health/welfare/sports etc, Woolston Hub has been closed for over a year, and the Council is not looking to re-open the facility, with their preferred option being to develop the site for more housing. The nearest leisure centre is in Salford, or Warrington town centre.
Ecology
The proximity and negative impact to several local ecological assets. There are key areas of nature conservation value and extensive areas of high-grade agricultural land that are within the planning site. It is important the landscape character is fully considered when deciding on future development. The Sites of Special Scientific Interest (SSSI) include Rixton Clay Pits
There are concerns on the testing for otters, voles, bats, and greater crested newts. The field exercise dismissed likelihood of otters. However, a search on local Facebook groups can prove these waters are often occupied by otters.
Documents presented in the planning application have conflicting reports on likelihood of protected species habitation. And no mitigation measures have been idented if these are positively identified.
The houses are proposed to be built with metres of the Manchester Ship Canal. It will be difficult for homeowners to get insurance for their properties. Current, and future climate change concerns are not addressed, localised flooding has become increasingly prevalent during the winter months, and levels of the Mersey and Ship Canal rise dramatically.
The National Planning Policy Framework states that the planning system should contribute to and enhance the natural and local environment by minimising impacts on biodiversity – this is currently unknown.
Consultation
The consultation exercise conducted on behalf of Peel Holdings, asked two particularly important questions, which have been ignored. The Statement of Community Involvement document asks.
“Do you agree that there is a local need for new homes in Hollins Green?” to which 91.2% say NO.
“Do you agree that this site is a suitable location to address local housing needs?” to which 90.8% said NO.
A request was made if Peel would meet for an open consultation with the villagers and told “[due to the results of survey questions above] The project team therefore sees little merit in organising an in-person consultation event as the response from the community is arguably conclusive and we do not expect that a drop in event would yield a different response.”
Was told by Peel (15/06/26) that 1,000 people were consulted, actual number was 583.